Automatic Transfer Switches
-
2 Pole 63A YCQ1B Automatic Transfer Switch | Reliable Power Backup
- Rs.6,700
Rs.7,400- Rs.6,700
- Unit price
- per
ATS 2 pole 63A is the right choice when a single-phase site needs automatic source transfer instead of a manual changeover handle. This model is listed at Rs.6,000 in Pakistan and suits homes, shops, offices, UPS backup boards, and small generator panels where automatic...- Rs.6,700
Rs.7,400- Rs.6,700
- Unit price
- per
-
4 Pole 63A YCQ1B Automatic Transfer Switch | Reliable Power Backup
- Rs.8,200
Rs.9,600- Rs.8,200
- Unit price
- per
ATS 4 pole 63A is the right choice when a three-phase board needs automatic source transfer instead of a manual changeover. This YCQ1B unit is listed at Rs.7,800 on CNC Electric Pakistan. It suits generator backup panels, small commercial buildings, workshops, lifts, pump rooms,...- Rs.8,200
Rs.9,600- Rs.8,200
- Unit price
- per
-
4 Pole 63A YCQR Automatic Transfer Switch | With Under Over Voltage Protection
- Rs.7,200
Rs.10,350- Rs.7,200
- Unit price
- per
Ensure uninterrupted power with the 4 Pole 63A YCQR Automatic Transfer Switch. Designed for seamless power transition, this switch offers reliable performance in critical applications across Pakistan. Key Features Automatic transfer for seamless power transition Under and over voltage protection 4 Pole, 63 Ampere...- Rs.7,200
Rs.10,350- Rs.7,200
- Unit price
- per
-
2 Pole 63A YCQR Automatic Transfer Switch | With Under Over Voltage Protection
- Rs.6,300
Rs.9,200- Rs.6,300
- Unit price
- per
Looking for an automatic transfer switch price in Pakistan for a home, office, shop, clinic, or backup panel that needs more intelligence than a plain ATS? This 2 Pole 63A YCQR unit from CNC Electric is listed at Rs. 8,250 and is built for...- Rs.6,300
Rs.9,200- Rs.6,300
- Unit price
- per
-
2 Pole 100A YCQ4 Automatic Transfer Switch | Reliable Power Changeover
- Rs.6,200
Rs.7,100- Rs.6,200
- Unit price
- per
Not sure which voltage protector you need? Try our VA Protector Product Finder Tool — Pakistan's first interactive selector. Automatic transfer switch buyers in Pakistan choose the 2 Pole 100A YCQ4 ATS Automatic Transfer Switch when they need budget ATS performance for real installations...- Rs.6,200
Rs.7,100- Rs.6,200
- Unit price
- per
-
4 Pole 100A YCQ4 Automatic Transfer Switch | Reliable Power Changeover Switch
- Rs.7,200
Rs.8,400- Rs.7,200
- Unit price
- per
ATS 4 pole 100A is built for panels that must shift from mains to backup supply without waiting for a person to flip a handle. This model is listed at Rs.7,500 on CNC Electric Pakistan. It suits generator changeover panels, small commercial backup boards,...- Rs.7,200
Rs.8,400- Rs.7,200
- Unit price
- per
-
DC 2 Pole 500V DC 100A YCQ4 Automatic Transfer Switch | Safe Solar Backup
- Rs.7,300
Rs.7,800- Rs.7,300
- Unit price
- per
General ● Functionality: Provides automatic switching to backup power when the main power supply fails. ● Applications: Automatic transfer switch widely used in households and other settings requiring uninterrupted power supply. ● Installation: Easy installation into household rail systems and compatible with Pz30 distribution boxes. ● Control: Offers both automatic...- Rs.7,300
Rs.7,800- Rs.7,300
- Unit price
- per
-
ATS 4 Pole 100A-630A | Heavy Duty Transfer
- Rs.18,500
Rs.24,000- Rs.18,500
- Unit price
- per
Automatic transfer switch buyers in Pakistan usually want one thing above all else: when utility power drops, the load should move to the standby source without a person running to the panel. This ATS 4 Pole heavy-duty range is listed on CNC Electric Pakistan...- Rs.18,500
Rs.24,000- Rs.18,500
- Unit price
- per
-
4 Pole Changeover Switch 63A-125A
- Rs.20,300
Rs.24,000- Rs.20,300
- Unit price
- per
Looking for an automatic transfer switch price in Pakistan for a generator-backed building, commercial site, or heavier three-phase changeover setup? This CNC Electric 4 pole ATS is built for automatic source shifting between utility power and backup generation, so the load moves without manual...- Rs.20,300
Rs.24,000- Rs.20,300
- Unit price
- per
Updated: May 2026 · CNC Electric Pakistan
Automatic Transfer Switch (ATS) — Pakistan Quick Answer (May 2026)
An Automatic Transfer Switch in Pakistan transfers electrical load from WAPDA / K-Electric mains to a backup generator or solar inverter automatically within 50–200 milliseconds of detecting power failure. Current CNC 2026 PKR prices range from Rs. 6,200 (2P 63A YCQ4) for small homes to Rs. 89,000 (4P 630A YCS1) for commercial loads.
| Generator / Load | Recommended CNC Model | 2026 Price (PKR) |
|---|---|---|
| Up to 5 kVA single-phase | YCQR 2P 63A | 6,300 |
| 5–15 kVA single-phase | YCQ4 2P 100A | 6,200 |
| 15–30 kVA 3-phase | YCQ1B 4P 63A | 8,200 |
| 30–100 kVA 3-phase | YCQ4 4P 100A | 7,200 |
| 100–300 kVA commercial | YCS1 4P 200–630A | 18,500–89,000 |
| Solar DC inverter switching | YCQ4 DC 2P 500V 100A | 7,300 |
Three common names, same device: automatic transfer switch (ATS) · automatic changeover switch · auto changeover switch. ✅ All CNC ATS units: 1-year warranty · IEC 60947-6-1 compliant · PSQCA-approved · same-day Lahore / Karachi / Islamabad delivery.
Read also: Automatic Changeover Switch Price Guide 2026 · ATS Buyer's Guide 2026
Automatic Transfer Switch (ATS) Price in Pakistan 2026 — Buyer's Guide
An Automatic Transfer Switch — ATS — automatically transfers your home or business load from WAPDA mains to a backup generator (or solar inverter) the moment it detects power loss, then transfers back when mains returns. Unlike a manual changeover switch which needs you to flip a handle, the ATS does it itself in 3-10 seconds — fast enough to keep IT equipment running, slow enough to let the generator stabilise. CNC stocks the YCQ1B, YCQR, YCQ4, and YCS1 series in 2-pole, 4-pole, 63 A through 630 A configurations from Rs. 6,200 to Rs. 89,000.
Every CNC ATS carries IEC 60947-6-1 compliance for transfer switching equipment, AC-33B utilisation category (frequent transfer between two sources), and a 5-year warranty. Stocked locally in Lahore for same-day dispatch nationwide.
CNC ATS Price Table — Pakistan 2026
| Model | Series | Poles | Current | Features | Price (PKR) |
|---|---|---|---|---|---|
| YCQ1B 2P 63A | Basic | 2 Pole | 63 A | Auto transfer, no protection | Rs. 6,700 |
| YCQ1B 4P 63A | Basic | 4 Pole | 63 A | 3-phase auto transfer | Rs. 8,200 |
| YCQR 2P 63A | Enhanced | 2 Pole | 63 A | Under/Over Voltage Protection | Rs. 6,300 |
| YCQR 4P 63A | Enhanced | 4 Pole | 63 A | 3-Phase + UV/OV Protection | Rs. 7,200 |
| YCQ4 2P 100A | Enhanced | 2 Pole | 100 A | Reliable changeover, 100A | Rs. 6,200 |
| YCQ4 4P 100A | Enhanced | 4 Pole | 100 A | 3-Phase 100A changeover | Rs. 7,200 |
| YCQ4 PV 2P 500V DC 100A | Solar | 2 Pole DC | 100 A @ 500V DC | Solar / Battery DC backup | Rs. 7,300 |
| YCS1 4P 200-630A | Heavy Duty | 4 Pole | 200-630 A (7 variants) | Industrial / commercial main | Rs. 18,500 – 89,000 |
| YCQ9 4P 63-125A | Generator | 4 Pole | 63-125 A (4 variants) | Generator dedicated changeover | Rs. 20,300 – 43,500 |
Free delivery across Pakistan. 5-year warranty. Bulk & dealer pricing — WhatsApp +92 326 1111376.
What Is an Automatic Transfer Switch?
An ATS is a relay-controlled switching device that constantly monitors the voltage and frequency on two power sources — typically WAPDA mains (the "preferred" source) and a generator or solar inverter (the "alternate" source). When the preferred source fails or its voltage drops outside acceptable limits, the ATS automatically opens the contacts on the failed source, waits for the alternate source to stabilise, then closes its contacts to feed the load from the alternate source.
Internally, an ATS combines three components:
- Two power switching mechanisms (one per source) — these are usually moulded-case contactor blocks, mechanically interlocked so both cannot close simultaneously.
- A voltage / frequency sensing controller — solid-state circuit monitoring both inputs. Typical thresholds: trip at < 170 V or > 275 V; restore at 200-260 V.
- A time-delay logic — to ride through brief WAPDA dips (0.5-3 s tolerance) and let the generator warm up after auto-start (10-30 s warm-up).
The control circuit is normally powered from whichever source is currently feeding the load, with backup capacitor / battery hold-up to ensure the controller can still switch even if both sources are momentarily dead.
ATS vs Manual Changeover Switch — Which Do You Need?
| Feature | Manual Changeover | Automatic Transfer Switch (ATS) |
|---|---|---|
| Transfer trigger | Human operator | Voltage / frequency sensor |
| Transfer time | 10-30 s plus walk time | 3-10 s (fully automatic) |
| Generator auto-start signal | No | Yes (sends start signal to genset) |
| Best for | Home, shop with manual-start genset | Office, server room, hospital, factory, auto-start genset |
| Price range (Pakistan) | Rs. 600 – 8,500 | Rs. 6,200 – 89,000+ |
| Service life | 10,000-30,000 operations | 3,000-15,000 transfer events |
| Maintenance | None | Annual relay / sensor check |
For most Pakistani homes with a manual-start generator, the cheaper manual changeover switch (Rs. 600 – 8,500) is the right answer. Step up to an ATS only when you have an auto-start generator, an unattended remote site, or 24-hour load that cannot tolerate manual switching delays (servers, hospitals, security systems).
ATS vs STS — What's the Difference?
The two terms are often confused:
- ATS (Automatic Transfer Switch): a slow-transfer device with 3-10 seconds of dead time during transfer. The load is briefly unpowered between sources. Used for general loads (lights, AC, motors, normal IT).
- STS (Static Transfer Switch): a high-speed transfer device using thyristors (SCRs) that transfers in 4-8 milliseconds — fast enough that even servers do not see the transfer. Used for critical IT, data centres, medical equipment that cannot tolerate any power dip.
ATS = electromechanical, cheap (Rs. 6,200+), 3-10 s dead time. STS = solid-state, expensive (Rs. 200,000+), 4-8 ms dead time. CNC stocks ATS only — for STS-class needs, a UPS plus ATS combination is usually the right answer.
Two Types of ATS — Open Transition vs Closed Transition
Within the ATS category, there are two transfer mechanisms:
- Open Transition (break-before-make): the ATS opens the failed source before closing the alternate source. A short dead-time (3-10 s) exists during the transfer. This is the safe default for nearly all installations — both sources are never connected together, eliminating risk of parallel short-circuit.
- Closed Transition (make-before-break): the ATS briefly parallels both sources for ~100 milliseconds, then opens the failed source. Zero dead time but requires the two sources to be synchronised (same frequency, voltage, phase). Used in data-center and hospital applications where even a brief blink is unacceptable.
CNC YCQ1B, YCQR, YCQ4, and YCS1 series are all open-transition ATS. They cannot parallel sources — by design — for safety. For closed-transition needs, specialised industrial ATS (Eaton ATC, Schneider ATyS) is required at 3-5× the price.
Where to Install an ATS
Home or shop with auto-start generator: Install the CNC YCQR 2P 63A (with under/over voltage protection) at the main DB box. Two inputs — WAPDA + generator. Outputs to home / shop bus. Wire the auto-start signal terminals to the generator panel.
3-phase commercial: Install the CNC YCQR 4P 63A or YCQ4 4P 100A at the panel main. For loads above 100 A, step up to YCS1 4P 200-630A.
Solar hybrid with grid backup: Use the CNC YCQ4 PV 2P 500V DC 100A on the DC side between solar/battery and inverter. Critical for installations where the battery may need to feed the inverter while the solar array is faulted, with auto-transfer back to solar when the fault clears.
Hospital / data center: Install YCS1 4P 200-630A at the main panel, with the generator's auto-start panel wired to the ATS control. Pair with downstream UPS for instantaneous transfer to critical loads during the 3-10 s ATS dead-time.
Factory / industrial: YCS1 4P 400-630A at the substation transformer secondary, with auto-start diesel generator backup.
Top Picks by Use Case
Best for Home with Auto-Start Generator: YCQR 2P 63A. Rs. 6,300 — adds under/over voltage protection so the ATS also disconnects on dangerous mains. View product →
Best Value (Basic Transfer): YCQ4 2P 100A. Rs. 6,200 — handles full home main up to 22 kW. Cheapest reliable ATS. View product →
Best for 3-Phase Commercial: YCQR 4P 63A. Rs. 7,200 — full 3-phase + neutral switching, with voltage protection. View product →
Best for Higher Current 3-Phase: YCQ4 4P 100A. Rs. 7,200 — 3-phase 100 A. View product →
Best for Solar / Battery DC: YCQ4 PV 2P 500V DC 100A. Rs. 7,300 — DC-rated for solar bypass and battery auto-transfer. View product →
Best for Factory / Industrial: YCS1 4P 200-630A. Rs. 18,500 – 89,000 — heavy-duty 3-phase ATS for substation-class loads. View product →
Best for Generator-Dedicated Changeover: YCQ9 4P 63-125A. Rs. 20,300 – 43,500 — purpose-built for generator changeover. View product →
CNC vs Schneider vs Chint vs Tomzn — ATS Brand Comparison
| Brand | Origin | Warranty | Voltage Protection | 3-Phase Variants | Price for 2P 63A |
|---|---|---|---|---|---|
| CNC YCQR | Imported, Lahore-stocked | 5 years | Yes (UV/OV built-in) | Yes (YCQR 4P) | Rs. 6,300 |
| Schneider ATyS | European premium | 3 years | Yes (programmable) | Yes (4P up to 6300A) | Rs. 28,000 – 45,000 |
| Chint NH40 | Imported (China) | 2 years | Yes (basic) | Yes (4P up to 1600A) | Rs. 9,500 – 14,000 |
| Tomzn (online) | Direct import | None | Yes (limited variants) | Limited | Rs. 8,500 – 12,000 |
| Socomec ATyS | European premium | 3 years | Yes (advanced) | Yes (4P up to 3200A) | Rs. 35,000+ |
| Eaton ATC | US premium | 3 years | Yes (closed transition option) | Yes (4P up to 6500A) | Rs. 80,000+ |
CNC sits in the imported-value tier — 4-7× cheaper than European/US premium for equivalent specifications on home / shop applications. The European brands win on industrial / mission-critical applications where closed-transition or programmable controls are needed.
ATS for Generator Auto-Start
Most modern diesel generators have a built-in auto-start panel with two signal terminals (typically labelled "Start" / "Stop" or "GEN START"). The CNC YCQR and YCS1 ATS series provide matching output contacts (Form C — Normally Open + Normally Closed) for these signals:
- When mains fails, ATS controller times out (typically 3 seconds to ride through brief dips)
- If mains is still gone, ATS closes its "GEN START" contact, sending the start signal to the generator panel
- Generator starts, warms up (typically 10-30 seconds for diesel), and stabilises voltage and frequency
- ATS detects acceptable generator voltage, opens the mains-side contacts, closes the generator-side contacts
- Load is now on generator
- When mains returns and remains stable for the "retransfer delay" (typically 30 seconds to 5 minutes), ATS switches back to mains
- After a cool-down delay (typically 5-10 minutes), ATS opens the GEN START contact, stopping the generator
Wiring: ATS "GEN START" Normally Open contact → in series with the generator's auto-start input (refer to your generator's wiring diagram for exact terminals).
Installation & Commissioning
- Switch OFF both source MCBs (WAPDA main + generator output).
- Mount the ATS in the main panel with adequate clearance for cable bends and ventilation.
- Connect WAPDA input to "Source 1" terminals, generator output to "Source 2" terminals. Use cables rated for the ATS amperage (10 mm² for 63 A, 25 mm² for 100 A, 50 mm²+ for 200 A+).
- Connect load output to the home / shop distribution bus.
- For 4-pole units, wire the neutral through the neutral pole (do not bypass).
- If using generator auto-start: wire the ATS "GEN START" Form C contact to the generator's start input.
- Power on WAPDA. Verify the ATS controller display shows mains-acceptable.
- Manually test by switching off the WAPDA main MCB. The ATS should signal the generator, wait for warm-up, then transfer to the generator side. Re-enable WAPDA and verify the ATS retransfers back.
Bulk & Dealer Pricing
CNC ATS units are stocked in Lahore with same-day dispatch nationwide. Bulk pricing for panel builders, generator installers, and solar contractors. Generator-paired bundles (ATS + voltage protector + SPD + DB box) priced separately. WhatsApp +92 326 1111376 with your project specification.
Frequently Asked Questions — ATS Pakistan
What is an automatic transfer switch?
An Automatic Transfer Switch (ATS) automatically transfers an electrical load between two power sources — typically WAPDA mains and a backup generator. When the preferred source fails, the ATS detects the failure, signals the generator to start, waits for the generator to stabilise, then transfers the load. It transfers back when mains returns. The transfer takes 3-10 seconds (open-transition design) and requires no human intervention.
What is the cost of an automatic transfer switch in Pakistan?
CNC ATS units range from Rs. 6,200 for the YCQ4 2P 100A (cheapest reliable home unit) to Rs. 89,000 for the YCS1 4P 630A (factory main panel). Mid-range 3-phase 63 A units cost Rs. 7,200 – 8,200. Premium European brands (Schneider, Socomec, Eaton) cost Rs. 28,000 – 80,000+ for equivalent ratings.
What are the two types of ATS?
The two ATS transfer mechanisms are: Open Transition (break-before-make) — opens the failed source before closing the alternate source, with a 3-10 second dead time during transfer; this is the safe default for nearly all installations. Closed Transition (make-before-break) — briefly parallels both sources for ~100 ms then opens the failed source, with zero dead time; requires synchronised sources and is used in data-center and hospital applications. CNC ATS units are all open-transition.
What is the difference between ATS and STS?
ATS (Automatic Transfer Switch) is an electromechanical device with 3-10 seconds dead time during transfer — cheap (Rs. 6,200+) but the load is briefly unpowered. STS (Static Transfer Switch) is a solid-state device using thyristors (SCRs) with 4-8 millisecond transfer time — expensive (Rs. 200,000+) but servers do not see the transfer. Use ATS for general loads; use STS for critical IT, data centres, and medical equipment that cannot tolerate any power dip.
What is the difference between ATS and a manual changeover switch?
A manual changeover switch requires a person to walk to the DB box and physically flip a handle (Rs. 600 – 8,500). An ATS transfers automatically based on voltage / frequency sensors (Rs. 6,200 – 89,000+), and can also signal the generator to auto-start. For unattended sites, auto-start generators, server rooms, hospitals, and 24-hour shops, the ATS is required. For homes with manual-start generators, the cheaper changeover is sufficient.
What size ATS do I need for my home?
Match the ATS rating to your main WAPDA breaker, not your generator. For most single-phase Pakistani homes (8-14 kW load), a 63 A 2-pole ATS is sufficient (CNC YCQR 2P 63A at Rs. 6,300). For larger homes or 3-phase connections, use the 100 A or 4-pole version. For factory / commercial main panels, step up to YCS1 4P 200-630 A.
Can an ATS work with solar inverter?
Yes. The CNC YCQ4 PV 2P 500V DC 100A is purpose-built for solar / battery auto-transfer. Install it on the DC side between solar / battery and the inverter. It automatically routes inverter input to whichever source (solar panels or battery) is currently producing acceptable voltage, with auto-transfer back when conditions change. For AC-side solar (grid-tie / net-metering), use a standard AC ATS like YCQR 2P 63A.
Does an ATS automatically start the generator?
Yes — when wired correctly. The CNC YCQR and YCS1 ATS units provide a Form C contact (Normally Open + Normally Closed) labelled "GEN START". Wire this to your generator's auto-start input (typically a 12V or 24V signal). When mains fails for longer than the ATS's "transfer delay" (typically 3 seconds), the ATS closes the GEN START contact, signalling the generator to start. After mains returns and is stable, the ATS opens the contact, signalling the generator to cool down and stop.
How long does an ATS last?
Mechanical life: 3,000-15,000 transfer events (each full switch from source A to source B and back). For typical use (5-10 outages per day in Pakistan during load-shedding), that is 5-15 years of service. The internal controller (solid-state) typically outlasts the mechanical contacts. CNC ATS units ship with a 5-year warranty covering controller and contact wear.
Can I install an ATS myself?
ATS installation involves connecting two live power sources at potentially high current (up to 630 A). Always hire a licensed electrician unless you are qualified for high-voltage switchgear work. Failures here can: back-feed live WAPDA lines (lineman injury), short the generator against mains (genset destruction), or leave the system permanently miswired. Installation cost: Rs. 3,500 – 10,000 depending on ATS size and panel complexity.
More CNC Electric Buyer's Guides
- DC Breaker Price in Pakistan 2026 — Solar & Battery Buyer's Guide
- Net Metering Pakistan 2026 — Cost, NEPRA Rules & Solar Protection
- MCCB Breaker Price in Pakistan 2026 — MCB vs MCCB vs RCCB Buyer's Guide
- Magnetic Contactor Price in Pakistan 2026 — 12A-265A CJX2s Buyer's Guide
- Voltage Protector vs Stabilizer 2026 — Which One Does Your Home Actually Need
- SPD Price in Pakistan 2026 — Surge Protection Device Buyer's Guide
- Electricity Meter Price in Pakistan 2026 — Digital, Smart & 3-Phase Buyer's Guide
- Solar DC Cable Price in Pakistan 2026 — 4mm & 6mm Buyer's Guide
- How to Choose a Voltage Protector / VA Protector — Selection Guide
- How to Wire SPD with Fuse + MCB + RCCB — Fire-Safe Surge Protection
- 1500V Industrial Solar Installation — DC Breaker, SPD, MCCB Sizing
- MCCB & ACB for Industrial Pakistan — Factory Switchgear
- MCB Wiring & Installation Guide — DB Box Layout, Torque
- AC Breaker for Air Conditioner — 1, 1.5, 2, 3 Ton Sizing
- Solar Combiner Box Wiring — DC Breaker, Fuse, SPD Step-by-Step
- EV Charger Pakistan 2026 — Home & Commercial Buyer's Guide
- CNC Industrial Range — Complete Factory Switchgear Roadmap
- Battery Bank Pakistan — LFP vs Lead-Acid Solar Battery Buyer's Guide
- Solar Inverter Pakistan — Hybrid, Grid-Tie, Off-Grid Selection
- MC4 Connectors Pakistan — Branded vs Generic, Crimping Guide
- PV String Sizing — Voc, Temperature Derating, Inverter Compatibility
- DC Fuse vs DC Breaker — Solar Strings, Batteries & SPD
- Off-Grid Solar System Design Pakistan — Complete Sizing Guide
- Why AC Breaker CANNOT Be Used on Solar — Physics & Risks
- CNC 1500V DC Solar Protection BOM — 100kW to 5MW
- 5 SPD Fire Case Studies Pakistan — Root Cause Analysis
Frequently Asked Questions
What is the price of an ATS in Pakistan in 2026?
CNC YCQ4 2-pole ATS 100A starts at PKR 35,000. YCS1 4-pole ATS 250A from PKR 65,000. PV-ATS (solar) variants similar prices.
How does an ATS work?
An ATS continuously monitors the primary source (grid). When voltage drops or disappears, it switches the load to the backup source (generator, solar, or inverter) within 1–3 seconds, then switches back when grid returns.
Will an ATS work with my Pakistani solar / inverter system?
Yes. CNC YCQ4 and PV-ATS units are tested with Solis, Growatt, Inverex, Knox and Maxpower inverters commonly used in Pakistan.
What size ATS do I need for a 7.5 kW system?
Use 63–100A 2-pole or 4-pole ATS depending on whether you have single-phase or 3-phase service. For 3-phase, the 4-pole ATS is required.
Is wiring an ATS DIY-friendly?
For licensed electricians yes — wiring follows standard 3-position transfer logic. For homeowners we recommend engaging a CNC authorised installer; misWiring can damage your inverter and void warranty.